REPORT ON KANAKA DURGA TEMPLE FLYOVER INDUSTRIAL VISIT

Visited :

KANAKA DURGA TEMPLE FLYOVER INDUSTRIAL VISIT

Date : 20-1-2016

No. of Students : 40

Faculty Cordinators :

  • V.AJAY KUMAR
  • P.NARESH

DESCRIPTION OF COMPANY :

Soma Enterprise Ltd. is one of the fastest growing infrastructure developers in India focused on construction and development of core infrastructure projects in the transportation, hydel power and water resource sectors among others.

According to information Soma Constructions bagged the contract. The firm quoted Rs. 282 crore for the project, and the works are started .The total cost of the project is estimated at Rs. 447.8 crore.

PROJECT DETAILS :

The much awaited work on the flyover at the kanaka durga temple in Vijayawada has been started on 5th Nov.

The bridge is expected to be a 6 lane flyover and it is Starts at Bhavanipuram Indian oil petrol bunk and its ends at beside Rajiv Gandhi park in to Vaaradhi.

The total length of fly over is 2.5 km and it contains a 50 piers The subways are two those are VMC office road to prakasam barrage and seethama paadhalu to durga ghat